OFF Grid System Design دانلود فایل اصلی

OFF GRID PV POWER SYSTEMS
SYSTEM DESIGN GUIDELINES
These guidelines have been developed by the Sustainable Energy Industry Association of the Pacific Islands in
Collaboration with the Pacific Power Association
They represent latest industry BEST PRACTICE for the design and installation of PV Grid Connect Systems.
© Copyright 2012
While all care has been taken to ensure this guideline is free from omission and error, no responsibility can be taken
for the use of this information in the design of any PV grid connect system.
Issue 1 September 2012 Page 1
GENERAL
The design of any off-grid system should consider, other than the electrical load, a number of criteria such as:
o Budget
o Power quality
o Environmental impact
o Aesthetics
o Acceptable genset runtime
o Noise levels
o Site accessibility
o Level of automation
Note: This guidelines are based on d.c. bus systems and do not include the new a.c. bus hybrid systems currently available. Guidelines dedicated to
hybrid Systems will be developed.
ENERGY SOURCE MATCHING
Heating and lighting should be supplied from the most appropriate source. For example –
o cooking – gas or wood burning stove
o water heating – solar water heating with gas or wood backup
o Lighting – electrical lighting most often used but natural light ( daylighting ) should be considered.
ENERGY EFFICIENCY
All appliances should be chosen for the lowest possible energy consumption for each desired outcome, such
as
o High efficiency lighting
o Energy efficient refrigeration
STANDARDS for DESIGN
System designs should follow any standards that are typically applied in the country or region where the solar
installation will occur. The following lists the relevant standards in Australia, New Zealand and USA They are
listed because some Pacific island countries and territories do follow those standards. These standards are
often updated and amended so the latest version should always be applied.
In Australia and New Zealand the main standards required include:
o AS/NZS3000 Wiring Rules
o AS/NZS4509 Stand-alone power systems
o AS 4086.2 Secondary batteries for stand-alone power supplies
o AS/NZS5033 PV Array
o AS 3010.1 Electrical Installations – Supply Generating set
o AS 1768 Lightning Protection
o AS 3595 Energy management programs
o AS 1359.51 Noise level limits
In USA PV systems must be in accordance with the following codes and standards:
o Electrical Codes-National Electrical Code Article 690:Solar Photovoltaic Systems and NFPA 70
Uniform Solar Energy Code
o Building Codes- ICC, ASCE 7
o UL Standard 1701: Flat Plat Photovoltaic Modules and Panels
o UL Standard 1741: Standard for Inverter, converters, Controllers and Interconnection System
Equipment for use with Distributed Energy Resources
Issue 1 September 2012 Page 2
INTRODUCTION
Four major issues arise when designing a system:
1. the load (power) required to be supplied by the system is not constant over the period of one day;
2. the daily energy usage varies over the year;
3. the energy available from the PV array may vary from time to time during the day;
4. the energy available from the PV array will vary from day to day during the year.
Since the system is based on photovoltaic modules, then a comparison should be undertaken between the
available energy from the sun and the actual energy demands The worst month is when the ratio between
solar energy available and energy demand is smallest.
The design of an off-grid power requires a number of steps. A basic design method follows:
1. Determination of the energy usage that the system must supply.
2. Determination of the battery storage required.
3. Determination of the energy input required from the PV array or other sources (eg battery
charger/generator)
4. Selection of the remainder of system components.
LOAD (ENERGY) ASSESSMENT
Electrical power is supplied from the batteries (DC) or via an inverter to produce either 230 volts AC (South
Pacific) or 110 / 120 volts AC (North Pacific). Electrical energy usage is normally expressed in watt hours (Wh)
or kilowatt hours ( kWh ).
To determine the daily energy usage for an appliance, multiply the power of the appliance by the number of
hours per day it will operate. The result is the energy (Wh) consumed by that appliance per day.
Appliances can either be DC or AC. An energy assessment should be undertaken for each type, examples of
these are shown in tables 1 and 2.
You need to calculate the electrical energy usage with the customer. Many systems have failed over the years
not because the equipment has failed or the system was installed incorrectly, BUT BECAUSE THE
CUSTOMER BELIEVED THEY COULD GET MORE ENERGY FROM THEIR SYSTEM THAN THE SYSTEM
COULD DELIVER. It failed because the customer was unaware of the power/energy limitations of the
system.
The problem is that the customer may not want to spend the time determining their realistic power and energy
needs which is required to successfully complete a load assessment form. They just want to know: How much
for a system to power my lights and TV?
A system designer can only design a system to meet the power and energy needs of the customer. The
system designer must therefore use this process to understand the needs of the customer and at the same
time educate the customer. Completing a load assessment form correctly (Refer to table 1 and 2 below) does
take time; you may need to spend 1 to 2 hours or more with the potential customer completing the tables. It is
during this process that you will discuss all the potential sources of energy that can meet their energy needs
and you can educate the customer on energy efficiency.
Issue 1 September 2012 Page 3
Worked Example
Table 1 DC Load (energy) Assessment
Table 2 AC Load (energy) Assessment
(1) (2) (3) (4a) (5a) (4b) (5b) (6) Comments
Appliance Number
Power
dry season wet season Contribution
to maximum
Usage demand
Time
Energy Usage
Time
Energy
W h Wh h Wh W
Light 4 7 4 112 4 112 28
Daily Load energy-d.c loads (Wh) ( DC 7a) 112 (DC 7b) 112
Maximum d.c. demand (W) (DC 8) 28
(1) (2) (3) (4a) (5a) (4b) (5b) (6) (7) (8) (9a) (9b)
Comments
Appliance No.
Power
dry season wet season
Power
Factor
Contribution
to max
demand Surge
Factor
Contribution to
surge demand
Usage
Time
Energy Usage
Time
Energy
Potential Design
W h Wh h Wh VA VA VA
TV 100 3 300 3 300 0.8 125 4 500 125
Refrigerator 100 12 1200 12 1200 0.8 125 4 500 500 Duty cycle of
0.5 included
Daily Load Energy A.C
Loads (Wh) (AC10a)
1500
(AC10b)
1500
maximum demand (VA) (AC11) 250 1000
Surge demand (VA) (AC12) 625
Issue 1 September 2012 Page 4
In the worked example on the previous page, the TV and refrigerator are using AC electricity so we have to
take into account the efficiency of the inverter. Typically the peak efficiency of the inverter may be over 90%
but in many systems the inverter will sometimes be running when there is very little load on the inverter, so the
average efficiency is about 85% to 90%. Then we must divide the total AC energy used by this figure to obtain
the energy required to be supplied to the inverter from the battery bank.
For the worked example assume the efficiency of the chosen inverter is 90%.
Daily battery load (energy) from AC loads = 1500Wh ¸ 0.9 = 1667 Wh
Daily battery load (energy) from DC loads = 112 Wh
To get the total load(energy) as seen by the battery, you add the two figures together:
1667 + 112= 1779Wh
If there are no AC loads, then you only have to work out the load from the DC appliances, and not include the
inverter (or the inverter efficiency).
BATTERY SELECTION
DETERMINATION OF SYSTEM VOLTAGE
System voltages are generally 12, 24 or 48 Volts. The actual voltage is determined by the requirements of the
system. For example, if the batteries and the inverter are a long way from the energy source then a higher
voltage may be required to minimise power loss in the cables. In larger systems 120V or 240V DC could be
used, but these are not typical household systems.
As a general rule, the recommended system voltage increases as the total load increases. For small daily
loads, a 12V system voltage can be used. For intermediate daily loads, 24V is used and for larger loads 48V is
used.
The changes over points are roughly at daily loads of 1 kWh and 3-4 kWh but this will also be dependent on
the actual power profile.
One of the general limitations is that maximum continuous current being drawn from the battery should not be
greater than 150A.
BATTERY SIZING
To convert Watt-hours (Wh) to Amp-hours (Ah) you need to divide by the battery system voltage.
For the worked example the daily energy usage was 1779Wh , so we select a battery system voltage of 24
Volts.
This means that the daily Ah demand on the batteries will be:
1 kWh 3-4 kWh
Use 12 Volt
system voltage
Use 24 Volt
system voltage
Use 48 Volt
system voltage
Issue 1 September 2012 Page 5
Ah = Wh ¸ system voltage 1779Wh ¸ 24 = 74 Ah
So at the moment the minimum size battery to meet the daily energy requirements in the example is: 74Ah
Battery capacity is determined by whichever is the greater of the following two requirements:
1. The ability of the battery to meet the energy demand of the system, often for a few days, sometimes
specified as ‘days of autonomy’ of the system;
OR
2. The ability of the battery to supply peak power demand.
The critical design parameters include:
Parameters relating to the energy requirements of the battery:
a) Daily energy demand
b) Daily and maximum depth of discharge
c) Number of days of autonomy
Parameters relating to the discharge power (current) of the battery:
a) Maximum power demand
b) Surge demand
Parameters relating to the charging of the battery:
a) Maximum Charging Current
Based on the these parameters there are a number of factors that will increase the battery capacity in order to
provide satisfactory performance. These correction factors must be considered.
1. Days of Autonomy
Extra capacity is necessary where the loads require power during periods of reduced input. The battery
bank is often sized to provide for a number of days autonomy. A common period selected is 5 days.
Where a generator is operating on a regular basis the autonomous period can be reduced.
In other cases, where there is no auxiliary charging source, the period of autonomy is often increased to 7
days or more.
For the worked example assume 5 days autonomy .
ADJUSTED
Battery Capacity = 74 x 5 = 370 Ah
2. Maximum Depth of Discharge
Battery manufacturers recommend a maximum depth of discharge (DOD). If this is regularly exceeded the
life of the battery is severely reduced. This could be 50% or for some solar batteries as high as 80%.
For the worked example Assume a maximum DOD of 70%.
ADJUSTED
Battery Capacity = 370 ¸ 0.7 = 529 Ah
3. Battery Discharge Rate
The actual discharge rate selected is highly dependent on the power usage rates of connected loads. Many
appliances operate for short periods only, drawing power for minutes rather than hours. This affects the battery
Issue 1 September 2012 Page 6
selected, as battery capacity varies with discharge rate. Information such as a power usage profile over the
course of an average day is required for an estimate of the appropriate discharge rate.
For small systems this is often impractical.
Where the average rates of power usage are low, the battery capacity for 5 days autonomy is often selected at
the 100hr rate of discharge for the battery.
For the worked example
ADJUSTED
Battery Capacity = 529 Ah (@ C100)
Where average power usage rates are high, it may be necessary to select the battery capacity for 5 days
autonomy at a higher discharge rate. eg. the 10 (C10) or 20hr (C20) rate
4. Battery Temperature derating
Battery capacity is affected by temperature. As the temperature goes down, the battery capacity reduces. The
following graph gives a battery correction factor for low temperature operation. Note that the temperature
correction factor is 1 at 25°C as this is the tempe rature at which battery capacity is specified.
In the tropics it is often still 20°C+ in the even ings so unless the system is located in a mountainous region
that does get cold then ignore the temperature derating. If you want to be conservative add 5% to the capacity
to allow for this factor.
BATTERY SELECTION
Deep discharge type batteries / cells should be selected for the required system voltage and capacity in a
single series string of battery cells.
Parallel strings of batteries are not recommended.
Where this is necessary each string must be separately fused.
For the worked example a battery of at least 529 Ah (@C100) should be used.
PV ARRAY SIZING- Standard Switched Controllers
The calculation for determining the size of the PV array is dependent on the type of controller used. Historically
standard switched controllers were the most common controllers used. In recent years a number of maximum
Issue 1 September 2012 Page 7
power point trackers (MPPT) have become available. This section determines how to size the PV array based
on switched controllers based on the PV array meeting the daily load requirements all year. Later in the guide
is a section on how to size a PV array using a MPPT.
The size of the PV array should be selected to take account of:
 seasonal variation of solar irradiation
 seasonal variation of the daily energy usage
 battery efficiency
 manufacturing tolerance of modules
 dirt
 temperature of array (the effective cell temperature)
Solar irradiation data is available from various sources. Some countries have data available from their
respective meteorological department. One source for solar irradiation data is the NASA website:
http:/eosweb.larc.nasa.gov/sse/. RETSCREEN, a program available from Canada, incorporates the NASA
data and it is easier to use. Please note that the NASA data has, in some instances, had higher irradiation
figures than that recorded by ground collection data in some countries. but if there is no other data available it
is data that can be used.
Solar irradiation is typically provided as kWh/m2 however it can be stated as daily peak Sun Hours (PSH). This
is the equivalent number of hours of solar irradiance of 1kW/m2.
Attachment 1 provides data on the following sites:
· Suva, Fiji (Latitude 18°08 S Longitude 178°25 E)
· Apia, Samoa (Latitude 13o50′ S’ Longitude 171o44′ W)
· Port Vila, Vanuatu (Latitude 17° 44′ S Longitude 168° 19′ E)
· Tarawa, Kiribati (Latitude 1°28’N, Longitude 173°2 ‘E)
· Raratonga, Cook islands( Latitude 21°30’S, Longitude 160°0’W)
· Nuku’alofa, Tonga (Latitude 21º14’S Longitude 175º22’W)
· Honiara, Solomon Islands (Latitude 09°27’S, Lon gitude 159°57’E)
· Koror ,Palau ( Latitude 7°20’N Longitude 134°28’E)
· Ponapei, Pohnpei FSM (Latitude: 6°54’N, Longitude : 158°13’E)
· Majuro, Marshall Islands (Latitude: 7º 12N, Longitude 171º 06E)
· Alofi, Niue (Latitude 19°04′ S. Longitude 169° 55′ W)
· Nauru (Latitude 0º55’S, Longitude 166º 91’E)
· Tuvalu (Latitude 8°31 S, Longitude 179°13 E)
· Hagåtña, Guam (Latitude 13°28 N Longitude: 144°45 E)
· Noumea, New Caledonia (Latitude 22°16 S Longitude: 166°27 E)
· Pago Pago, American Samoa (Latitude 14°16  S Longitude: 170°42 W)
The variation of both the solar irradiation and the load energy requirement should be considered. If there is no
variation in daily load between the various times of the year then the system should be designed on the month
with the lowest irradiation that is peak sun hours (PSH).
DAILY ENERGY REQUIREMENT FROM THE PV ARRAY
In order to determine the energy required from the PV array, it is necessary to increase the energy from the
battery bank to account for battery efficiency.
.
The average columbic efficiency (in terms of Ah) of a new battery is 90% (variations in battery voltage are not
considered).
For the worked example the daily energy requirement expressed in Ah from the battery is 74 Ah. Allowing for
the battery efficiency, the solar array then needs to produce…
74 Ah ¸ 0.9 = 82.2 Ah
Assume the worst months PSH is 5.
Issue 1 September 2012 Page 8
Therefore the required PV array output current is:
82.2 Ah ¸ 5 PSH = 16.5 A
OVERSIZE FACTOR
If the system does not include a fuel generator which can provide extra charging to the battery bank then the
solar array should be oversized to provide the equalisation charging of the battery bank. In Australia and New
Zealand this is between 30% and 100%. It is recommended in the Pacific that this is 10%.
For the worked example the adjusted array output current is:
16.5A x 1.1 = 18.1 A
DERATING MODULE PERFORMANCE
The PV array will be de-rated due to:
· Manufacturer’s Tolerance: Most manufacturers rate their modules ± a percentage (eg ±3%) or wattage
(eg ±2W). Unless every module is tested and its actual rating is known then the modules should be derated
by the manufacturer’s tolerance.
· Dirt: Over a period of time dirt or salt (if located near the coast) can build up on the array and reduce
the output. The output of the module should therefore be derated to reflect this soiling. The actual value
will be dependent on the site but this can vary from 0.9 to 1 (i.e. up to 10% loss due to dirt).
· Temperature: Modules’ output power decreases with temperature above 25°C and increases with
temperatures below 25°C. The average cell temperatu re will be higher than the ambient because of the
glass on the front of the module and the fact that the module absorbs some heat from the sun. The
output power and/or current of the module must be based on the effective temperature of the cell. This
is determined by the following formula:
Tcell-eff = Ta.day + 25°C
Where
Tcell-eff = the average daily effective cell temperature in degrees Celsius (°C)
Ta.day = the daytime average ambient temperature for the month that the sizing is being undertaken.
Since the modules are used for battery charging, the current at 14 Volts (a good battery charging voltage) at
the effective cell temperature should be used in calculations. If curves are unavailable to determine the current
at effective cell temperature then use the Normal Operating Cell temperature (NOCT) provided by the
manufacturers.
Therefore the derated module output current is calculated as follows:
The Current of the module at 14V and effective cell temperature (or NOCT current)
multiplied by derating due to manufacturers tolerance
multiplied by derating due to dirt
I (NOCT) x fman x fdirt
If a module has a 3% (0.03) manufacturers tolerance, then the module current is derated by multiplying by
0.97 (1-0.03).
If a module has a 5% (0.05) loss due to dirt then the module current is derated by multiplying by 0.95 (1-0.05).
For the worked example the selected module has a peak rating of 80WP.
An 80 watt solar module (still used in many small off-grid systems) typically has the following data:
Issue 1 September 2012 Page 9
Table 3: 80 W module data
Rated Power 80W
Power Tolerance ± 5%
Nominal Voltage 12V
Maximum Power Voltage, Vmp 17.6V
Maximum Power Current, Imp 4.55A
Open Circuit Voltage, Voc 22.1V
Short Circuit Current, Isc 4.8A
NOCT 47±2°C
Current at 14V and NOCT 4.75A
Assuming a 5% dirt derating then the adjusted output current of the above module is:
ADJUSTED
Module current = I (NOCT) x 0.95 ( ¬ minus 5% for manufactures tol) x 0.95 ( ¬ minus 5% for dirt)
= 4.75A x 0.95 x 0.95 = 4.29A
NUMBER OF MODULES REQUIRED IN ARRAY
First determine number of modules in series, To do this divide the system voltage by the nominal operating
voltage of each module. In our example:
For the worked example Number of modules in series = 24V ¸ 12V = 2
Therefore the array must comprise of series connected strings of 2 modules.
To determine the number of strings in parallel, the PV array output current required (in A) is divided by the
output of each module (in A).
For the worked example Number of strings in parallel =18.1A ¸ 4.29A = 4.22
Do we round up or down? If you want to be conservative you would round up. However in this example we
suggest you round down since this calculation was based on the worst month and we allowed an oversize of
10%.This does need to be determined for each system.
For the worked example The number of modules in the array = 4 x 2 = 8
The peak rating of the array is : 8 x 80WP = 640WP
INVERTER SELECTION
The type of inverter selected for the installation depends on factors such as cost, surge requirements, power
quality and for inverter/chargers, a reduction of the number of system components necessary. Inverters are
available in 3 basic output types – Square wave, modified square wave and sine wave.
There are few square wave inverters used today.
Modified square wave inverters generally have good surge and continuous capability and are usually cheaper
than sine wave types. However, some appliances, such as audio equipment, television and fans can suffer
because of the output wave shape.
Sine wave inverters often provide a better quality power than the 230V (or 110V or 120V) grid supply.
Issue 1 September 2012 Page 10
INVERTER SIZING
The selected inverter should be capable of supplying continuous power to all AC loads
AND
providing sufficient surge capability to start any loads that may surge when turned on and particularly if they
turn on at the same time.
Where an inverter cannot meet the above requirements attention needs to be given to load control and
prioritisation strategies.
For the worked example
From the load (energy) assessment on page 3, a selected inverter must be capable of supplying 250VA
continuous with a surge capability of 625VA.
CONTROLLERS- Standard Switched Controller
PV controllers on the market range from simple switched units that only prevent the overcharge (and
discharge) of connected batteries to microprocessor based units that incorporate many additional features
such as …
o PWM and equalisation charge modes
o DC Load control
o Voltage and current metering
o Amp-hour logging
o Generator start/stop control
Unless the controller is a model that is currently limited these should be sized so that they are capable of
carrying 125% of the array short circuit current and withstanding the open circuit voltage of the array. If there is
a possibility that the array could be increased in the future then the controller should be oversized to cater for
the future growth.
(Note: sometimes the controller is called a regulator)
For the worked example
The controller chosen must have a current rating
> 1.25 x 4 x 4.8 A = 24A at a system voltage of 24V.
GENERATORS & BATTERY CHARGING
To reduce system costs, it is common for some form of auxiliary charging to be used to provide energy when
daily energy requirements are greater than the daily PV input into the system. This is usually a
diesel/petrol/gas powered generator. Where the electrical output is 230V AC (or 110V or 120V) a battery
charger is required.
An inverter/charger can be used; otherwise a separate charger unit is needed.
Factors that must be considered when using internal combustion generators are
o Fuel storage and spillage precautions
o Noise emission control
o Ventilation
o Generator loading
With regards to generator loading, a generator should supply greater than 50% of its maximum rating while
running. Loading of less than 50% increases running and maintenance costs and reduces generator life.
Issue 1 September 2012 Page 11
( refer to genset manufacturers’ information )
BATTERY CHARGER SIZING
A charger must be capable of supplying voltage greater than the nominal system voltage.
The maximum charging current must not be greater than that recommended by the battery manufacturer but a
usable estimate is a maximum charge current of around 10% of the C10 rate.
PV ARRAY SIZING- MPPT
DAILY ENERGY REQUIREMENT FROM THE PV ARRAY
The size of the PV array should be selected to take account of:
 seasonal variation of solar irradiation
 seasonal variation of the daily energy usage
 battery efficiency (wh)
 Cable losses
 MPPT efficiency
 manufacturing tolerance of modules
 dirt
 temperature of array (the effective cell temperature)
With the standard controller the only sub-system losses was the battery efficiency and the calculations are
undertaken using Ah. When using a MPPT the calculations are in Wh and the sub-system losses in the system
include:
· Battery efficiency (watthr)
· Cable losses
· MPPT efficiency
In order to determine the energy required from the PV array, it is necessary to increase the energy from the
battery bank to account for all the sub-system losses.
For the worked example assume cable losses is 3% (transmission efficiency of 97%), MPPT efficiency of 95%
and battery efficiency of 80%
Subsystem efficiency = 0.97 x 0.95 x 0.8 = 0.737
Energy required from the PV array = 1779Wh ¸ 0.737 = 2413Wh
Assume the worst months PSH is 5.
Therefore the required peak PV array output power is:
2413Wh ¸ 5 PSH = 482WP
OVERSIZE FACTOR
If the system does not include a fuel generator which can provide extra charging to the battery bank then the
solar array should be oversized to provide the equalisation charging of the battery bank. In Australia and New
Zealand this is between 30% and 100%. It is recommended in the Pacific that this is 10%.
For the worked example Therefore the adjusted array output current is:
482WP x 1.1 = 530WP
DERATING MODULE PERFORMANCE
The PV array will be de-rated due to:
Issue 1 September 2012 Page 12
· Manufacturer’s Tolerance: Most manufacturers rate their modules ± a percentage (eg ±5%) or wattage
(eg ±2W). Unless every module is tested and its actual rating is known then the modules should be derated
by the manufacturer’s tolerance.
· Dirt: Over a period of time dirt or salt (if located near the coast) can build up on the array and reduce
the output. The output of the module should therefore be derated to reflect this soiling. The actual value
will be dependent on the site but this can vary from 0.9 to 1 (i.e. up to 10% loss due to dirt).
· Temperature: Modules’ output power decreases with temperature above 25°C and increases with
temperatures below 25°C. The average cell temperatu re will be higher than the ambient temperature
because of the glass on the front of the module and the fact that the module absorbs some heat from
the sun. The output power and/or current of the module must be based on the effective temperature of
the cell. This is determined by the following formula:
Tcell-eff = Ta.day + 25°C
Where
Tcell-eff = the average daily effective cell temperature in degrees Celsius (°C)
Ta.day = the daytime average ambient temperature for the month that the sizing is being undertaken.
With switched controllers the temperature effect was used to determine the operating current of the
module/array. With MPPT’s the derating power factor must be calculated.
The three main types solar modules available on the market each have different temperature coefficients.
These are:
· Monocrystalline: Modules typically have a temperature coefficient of –0.45%/oC. That is for every
degree above 25oC the output power is derated by 0.45%.
· Polycrystalline: Modules typically have a temperature coefficient of –0.5%/oC.
· Thin Film: Modules have a different temperature characteristic resulting in a lower co-efficient typically
around 0%/°C to -0.25%/°C, but remember to check with the manufacturer
The typical ambient daytime temperature in many parts of the Pacific is between 30 and 35oC during some
times of the year. So it would not be uncommon to have module cell temperatures of 55oC or higher.
For the worked example Assume the ambient temperature is 30oC..
Therefore the effective cell temperature is
30oC +25oC = 55oC
Therefore this is 30oC above the STC temperature of 25oC.
The 80 WP module used in this example is a polycrystalline module with a derating of -0.5%/oC
Therefore the losses due to temperature would be:
Temperature loss = 30oC x 0.5%/oC = 15% loss
This is a temperature derating factor of 0.85
Assuming a 5% dirt derating then the adjusted output power of the 80W module is:
Adjusted module power = 80 x 0.95 x 0.95 x 0.85 = 61.4W
NUMBER OF MODULES REQUIRED IN ARRAY
To calculate the required number of modules in the array, divide the required array power by the adjusted
module power.
Issue 1 September 2012 Page 13
For the worked example
Number of modules in array =530 ¸ 61.4 = 8.63
(Note for the switch regulator we had 4.29 parallel strings of 2 modules in series)
The actual number of modules will be dependent on the MPPT selected. If it was 9 then the rating of the array
is : 9 x 80WP = 720WP
SELECTING MPPT
The following table gives some examples of MPPT’s currently available on the market:
Table 4: MPPT Data
Model d.c. battery
Voltage (V)
Input voltage
range (V)
Max d.c.
Battery
Current (A)
Max(W) Solar
Array
Max Load
Current (A)
STECA
Solarix
MMP2010
12/24 17 to 100 20 250/500 10
Phocos
MMPT
100/20-1
12/24 Max 95 20 300/600 10
Morningstar
SS-MPPT-15L
12/24 Max 75 15 200/400 15
Outback Flex
Max 80
12/24/36/48/60 Max 150 80 1250(12)
2550(24)
5000(48)
7500 (60)
Outback Flex
Max60
12/24/36/48/60 Max 150 60 900(12)
1800(24)
3600(48)
4500 (60)
For the worked example
Allowing for 125% oversizing then the required rating of the MPPT is:
1.25 x 720Wp = 900 W
From the table we would select the Outback Flexmax60 which has an array rating of 1800W @ 24V
We could possibly use two of the others e.g. Phocos or Steca.
MATCHING THE PV ARRAY TO THE MAXIMUM VOLTAGE SPECIFICATIONS OF THE MPPT
The MPPT typically have a recommended minimum nominal array voltage and a maximum voltage. In the
case where a maximum input voltage is specified and the array voltage is above the maximum specified, the
MPPT could be damaged.
Some MPPT controllers might allow that the minimum array nominal voltage is that of the battery bank.
However the MPPT will work better when the minimum nominal array voltage is higher than the nominal
voltage of the battery. The Outback range of MPPT’s requires that the minimum nominal array voltage is
greater as shown in Table 5. Please check with the MPPT manufacturer because these could vary.
Issue 1 September 2012 Page 14
Table 5 Minimum Nominal Array Voltages (Outback MPPT’s)
Nominal Battery Voltage Recommended Minimum Nominal Array
voltage
12V 24V
24V 36V
48V 60V
It is important that the output voltage of the string is matched to the operating voltages of the MPPT and that
the maximum voltage of the MPPT is never reached.
The output voltage of a module is affected by cell temperature changes in a similar way to the output power.
The manufacturers will provide a voltage temperature coefficient. It is generally specified in V/°C (or mV/°C)
but it can also be expressed as a % .
To ensure that the Voc of the array does not reach the maximum allowable voltage of the MPPT the minimum
day time temperatures for that specific site are required.
In early morning at first light the cell temperature will be very similar to the ambient temperature because the
sun has not had time to heat up the module. In the Pacific Islands the average minimum temperature is 200C
(this could be lower in some mountain areas) and it is recommended that this temperature is used to
determine the maximum Voc. (Note: If installing in the mountains then use the appropriate minimum
temperature. Many people also use 0°C, if appropriate for the ar ea). The maximum open circuit voltage is
determined similar to the temperature derating factor for the power.
For the worked example Assume the voltage co-efficient is 0.07V/oC.
If the minimum temperature is 20oC this is 5oC below the STC temperature of 25oC. Therefore the effective
variation in voltage is:
5 x 0.07 = 0.35V
So the maximum open circuit voltage of the module = 22.1V + 0.35V =22.45V
Maximum number of modules that you can have in series = 150V ¸ 22.45V = 6.68 this is rounded down to 6.
So the MPPT will allow between 3 and 6 modules in a string.
The actual number of modules required was 8.68. If we round down to 8 (since an oversize factor of 10% and
also worst month for PSH was used) then the array would be 2 parallel strings of 4 modules in series. If we
round up to 9 then the solution could be 3 parallel strings with 3 modules in series.
Issue 1 September 2012 Page 15
ATTACHMENT 1: : Table showing Peak Sunhrs for various sites and tilt angles.
Location Peak Sunlight Hours (kWh/m²/day)
Suva, Fiji Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 18°08  South 0° Tilt ¹ 6.29 6.2 5.54 4.67 4.05 3.72 3.89 4.44 5.08 6.04 6.32 6.38 5.21
Longitude: 178°25  East 18° Tilt ² 6.27 5.88 5.55 4.99 4.61 4.38 4.51 4.88 5.22 5.83 6.1 6.41 5.38
33° Tilt ² 5.95 5.4 5.33 5.03 4.85 4.7 4.8 5 5.1 5.43 5.71 6.12 5.29
Apia, Samoa Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 13°50  South 0° Tilt ¹ 5.39 5.47 5.16 5.09 4.63 4.46 4.71 5.25 5.77 5.91 5.76 5.51 5.25
Longitude: 171°46  West 13° Tilt ² 5.31 5.24 5.12 5.32 5.07 5 5.24 5.61 5.85 5.72 5.67 5.45 5.38
28° Tilt ² 5.13 4.86 4.93 5.38 5.36 5.42 5.64 5.81 5.75 5.36 5.45 5.3 5.37
Port Vila, Vanuatu Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 17°44  South 0° Tilt ¹ 6.68 6.2 5.76 4.98 4.2 3.79 4.04 4.75 5.65 6.47 6.67 6.93 5.5
Longitude: 168°19  East 17° Tilt ² 6.69 5.9 5.78 5.33 4.76 4.42 4.66 5.22 5.82 6.26 6.46 7.01 5.69
32° Tilt ² 6.38 5.43 5.56 5.39 5.02 4.75 4.98 5.39 5.72 5.83 6.07 6.73 5.61
Tarawa, Kiribati Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 01°28  North 0° Tilt ¹ 5.58 5.98 5.99 5.87 5.82 5.7 5.87 6.15 6.52 6.4 6.1 5.5 5.95
Longitude: 173°02  East 16° Tilt ² 5.9 6.11 5.83 5.79 5.94 5.92 6.06 6.17 6.28 6.45 6.43 5.88 6.06
Rarotonga, Cook Islands Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 21°12  South 0° Tilt ¹ 6.45 6.14 5.78 4.59 3.86 3.54 3.73 4.46 5.16 5.94 6.63 6.56 5.23
Longitude: 159°47  West 21° Tilt ² 5.9 5.82 5.86 5.04 4.56 4.2 4.35 5.07 5.39 5.74 6.11 6.51 5.38
36° Tilt ² 5.19 5.34 5.62 5.08 4.8 4.49 4.6 5.22 5.27 5.35 5.41 6.11 5.21
Issue 1 September 2012 Page 16
Nuku’alofa, Tongatapu, Tonga Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 21°08  South 0° Tilt ¹ 6.69 6.3 5.62 4.65 4.04 3.58 3.78 4.43 5.23 6.28 6.69 6.7 5.32
Longitude: 175°12  West 21° Tilt ² 6.1 5.97 5.69 5.1 4.81 4.25 4.41 5.03 5.46 6.08 6.16 6.65 5.48
36° Tilt ² 5.35 5.47 5.46 5.14 5.08 4.55 4.68 5.18 5.34 5.65 5.45 6.25 5.3
Honiara, Solomon Islands Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 09°27  South 0° Tilt ¹ 5.99 5.55 5.61 5.41 4.76 4.59 4.45 5.19 5.81 6.26 6.4 6.22 5.52
Longitude: 159°57  East 9° Tilt ² 5.98 5.47 5.54 5.52 5.01 4.91 4.7 5.36 5.82 6.15 6.38 6.24 5.59
24° Tilt ² 5.91 5.29 5.35 5.59 5.27 5.28 4.99 5.53 5.72 5.88 6.28 6.22 5.61
Koror, Palau Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 07°20  North 0° Tilt ¹ 5.19 5.59 6.18 6.3 5.71 5.01 5.12 5.2 5.56 5.39 5.26 4.94 5.45
Longitude: 134°28  East 7° Tilt ² 5.4 5.7 6.16 6.22 5.7 5.01 5.11 5.15 5.49 5.45 5.44 5.16 5.5
22° Tilt ² 5.75 5.86 6.06 6.01 5.66 5.03 5.1 5.03 5.3 5.51 5.74 5.54 5.55
Ponape, Pohnpei FSM Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 6°54  North 0° Tilt ¹ 4.97 5.57 5.91 5.79 5.44 5.33 5.51 5.54 5.66 5.29 5.03 4.83 5.4
Longitude: 158°13  East 6° Tilt ² 5.12 5.65 5.88 5.72 5.42 5.33 5.51 5.49 5.59 5.33 5.16 5 5.43
21° Tilt ² 5.43 5.82 5.8 5.55 5.4 5.39 5.53 5.39 5.41 5.39 5.43 5.36 5.49
Majuro, Marshall Islands Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 7°12  North 0° Tilt ¹ 5.26 5.86 6.11 5.89 5.66 5.31 5.35 5.63 5.42 5.15 4.88 4.84 5.44
Longitude: 171°06  East 7° Tilt ² 5.47 5.99 6.09 5.81 5.65 5.32 5.35 5.58 5.35 5.2 5.03 5.05 5.49
22° Tilt ² 5.83 6.16 5.99 5.62 5.61 5.35 5.35 5.46 5.16 5.25 5.27 5.4 5.53
Issue 1 September 2012 Page 17
Alofi, Niue Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 19°04  South 0° Tilt ¹ 6.47 6.2 5.67 4.8 4.26 3.86 4.01 4.61 5.35 6.02 6.53 6.46 5.34
Longitude: 169°55  West 19° Tilt ² 6.43 5.88 5.7 5.2 4.96 4.47 4.75 5.14 5.53 5.81 5.98 6.47 5.53
34° Tilt ² 6.06 5.4 5.47 5.24 5.24 4.78 5.08 5.29 5.42 5.41 5.35 6.15 5.41
Nauru Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 0°32  South 0°Tilt ¹ 5.77 6.24 6.27 6.04 5.99 5.75 5.85 6.25 6.7 6.5 6.12 5.5 6.07
Longitude: 166°56  East 15° Tilt ² 5.94 6.26 6.07 6.06 6.28 6.16 6.21 6.4 6.52 6.45 6.27 5.69 6.19
Vaiaku, Tuvalu Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 8°31  South 0° Tilt ¹ 5.16 5.27 5.33 5.29 4.93 4.66 4.76 5.3 5.72 5.8 5.57 5.23 5.25
Longitude: 179°13  East 8° Tilt ² 5.14 5.2 5.26 5.37 5.14 4.92 5 5.45 5.71 5.71 5.54 5.22 5.31
23° Tilt ² 5.09 5.05 5.08 5.43 5.42 5.3 5.33 5.62 5.61 5.49 5.47 5.21 5.34
Hagåtña, Guam Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 13°28  North 0° Tilt ¹ 5.33 5.87 6.73 7.12 7.04 6.44 6 5.3 5.42 5.46 5.16 5.05 5.9
Longitude: 144°45  East 13° Tilt ² 5.95 6.27 6.86 6.88 6.97 6.43 5.95 5.06 5.38 5.7 5.66 5.7 6.07
28° Tilt ² 6.41 6.49 6.75 6.4 6.7 6.27 5.76 4.68 5.19 5.78 6.01 6.2 6.05
Noumea, New Caledonia Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 22°16  South 0° Tilt ¹ 7.31 6.7 5.73 4.97 3.94 3.47 3.91 4.73 6.05 7.09 7.41 7.6 5.73
Longitude: 166°27  East 22° Tilt ² 6.61 6.34 5.83 5.56 4.76 4.19 4.69 5.51 6.44 6.88 6.77 7.53 5.93
37° Tilt ² 5.75 5.8 5.6 5.63 5.03 4.48 5 5.7 6.33 6.38 5.94 7.03 5.72
Pago Pago, American Samoa Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Average
Latitude: 14°16  South 0° Tilt ¹ 5.87 5.93 5.54 5.18 4.63 4.4 4.59 5.2 5.78 6.05 6.11 5.93 5.43
Longitude: 170°42  West 14° Tilt ² 5.79 5.66 5.51 5.43 5.11 4.99 5.15 5.59 5.88 5.84 6.01 5.87 5.57
Issue 1 September 2012 Page 18
29° Tilt ² 5.57 5.22 5.3 5.49 5.4 5.39 5.52 5.77 5.77 5.46 5.75 5.68 5.53
¹ Monthly Averaged Insolation Incident On A Horizontal Surface (kWh/m²/day)
² Monthly Averaged Irradiation Incident On An Equator-Pointed Tilted Surface (kWh/m²/day)
Source: NASA Surface meteorology and Solar Energy
(http://eosweb.larc.nasa.gov)
Issue 1 September 2012 Page 19
Appendix 1 – Table of Abbreviations and Acronyms
d.c. Direct current
a.c. Alternating current
AS/NZS Australia Standard/New Zealand Standard
UL Underwriters Laboratory
ICC International Code Council
NFPA National fire Protection Association
ASCE American Society of Civil Engineers
IEEE Institute of Electrical and Electronics Engineers
Wh Watt hours
kWh Kilowatt hours
W Watts
WP Watts peak
H hours
V Volts
A Amps
VA Volt amps
Ah Amp hours
DOD Depth of discharge
C100 Battery capacity when battery is discharged over 100
hours
PV Photovoltaic
MPPT Maximum power point tracker
PSH Peak sun hours( kWh/m2)
kWh/m2 Kilowatt hours/metres squared
°C Degrees Celsius
NOCT Nominal operating cell temperature
Tcell-eff the average daily effective cell temperature (degrees
Celsius)
Ta.day the daytime average ambient temperature for the month
that the sizing is being undertaken (degrees Celsius)
fman Derating due to manufacturers tolerance
(dimensionless)
fdirt Derating due to dirt (dimensionless)
PWM Pulse Width Modulation
Voc Open circuit voltage (volts)
Vmp Maximum power point voltage (volts)
Isc Short circuit current (amps)
Imp Maximum power point current (amps)
STC Standard test conditions

درباره نادیا رودسرابی

ارسال دیدگاه

نشانی ایمیل شما منتشر نخواهد شد. بخش‌های موردنیاز علامت‌گذاری شده‌اند *

  • 4 × 4 =